Downtown Revitalization Project Update #11
As everyone in Town has seen, there has been a lot happening to our Downtown! Here is our weekly update recapping last week and talking about the plans for this week.
Last Week:
-
New streetlights were installed on Dawson Street
-
Sidewalk and boulevard were removed along the east side of Meredith Street
-
Water service replacement began on Meredith Street
- New and improved parking lot lines as planned to support parking during the construction on Meredith Street (Both sides of Town Office/Library Parking Lots, new lines on Eleanor St, new lines in Main Parking Lot)
This Week:
-
Water service replacement continues along the east side of Meredith toward Main Street
-
Touch-ups are underway on Dawson Street
-
Street banners will hopefully be installed on the new light poles
-
Masts will be set up at the end of Dawson Street
Thank you to everyone for your continued patience and support as we improve our downtown core.